When constructing a tunnel, like the Vedeggio-Cassarate Tunnel, a new place in the city is also created, destined in a short time - since its opening on July 26, 2012 - to change the geography of all surrounding areas. For this reason, the tunnel is not a standalone project but part of a series of works and interventions (Piano dei trasporti del Luganese, PTL) that affect the Lugano area and integrate with one another.

The Vedeggio-Cassarate Tunnel is 2,630 meters long, accommodates bidirectional traffic, crosses the hill of the municipalities of Comano, Cureglia and Porza, and connects the Vedeggio Valley with the Cassarate Valley: more precisely, the Lugano Nord motorway exit and Via Sonvico in Canobbio.

Brief history of the project

  • 2005: Start of construction
  • 2006: Completion of the safety tunnel excavation
  • 2006: Commissioning of the roundabout (Vedeggio portal)
  • 2009: Breakthrough of the final rock diaphragm
  • 2012: Completion and opening

The English version of this page was created with the aid of automatic translation tools and may contain errors and omissions.

The original version is the page in Italian.

Contacts

Repubblica e Cantone Ticino
Piano dei Trasporti del Luganese (PTL)
Via Franco Zorzi 13
6501 Bellinzona
t. +41 91 815 90 91
www.ti.ch/ptl